Lance Ferris Wharf Ballina

ProjectLance Ferris Wharf Ballina

There were many aspects to this project we needed to be aware of including that there were different berthing requirements, a sloping sea bed, and minimising long term maintenance.

The Brief:
The client came to us wanting a traditional timber wharf system which could withstand large berthing loads from occasional large vessels as well as accommodating more frequent smaller vessels

Key Challenges:
The key challenges we could see for this project were developing the building design and project scope to meet the requirements of the tenant.

Solutions:
The key challenges we could see for this project were different berthing requirements, a sloping sea bed, and minimising long term maintenance.

Key Features:
The key features/points of difference to mention of the project are, the dual berthing system, and the overall value for money, low maintenance cost wharf that we achieved.

APP's Role:
Ardill Payne & Partners were responsible for the Structural Design of the wharf.

Timeframe
The project was completed in one and a half years.

Budget
The budget for the project was $700,000.